SBC for engineering surveys for construction. Directory of basic prices for engineering surveys for construction. engineering and geodetic surveys during the construction and operation of buildings and structures of JSC "PNIIS". and operation of buildings and structures

STATE COMMITTEE OF THE RUSSIAN FEDERATION
ON CONSTRUCTION AND HOUSING AND COMMUNAL COMPLEX

(GOSSTROY RUSSIA)

BASIC PRICE GUIDE
FOR ENGINEERING SURVEYS
FOR CONSTRUCTION

ENGINEERING AND GEODESIC SURVEYS

(prices are adjusted to the base level as of 01/01/2001)

Moscow 2004

DEVELOPED BY FSUE "PNIIIS" (T.A. Larina, S.I. Rykhlova, N.I. Chushkina), JSC "Institute Gidroproekt" (E.A. Nikanorov, Yu.A. Kharkov), LLC "NPC Ingeodin" ( Kalbergenov G.G., Larin V.V.) with the participation of FSUE Aeroproekt, Committee on Architecture and Urban Planning Krasnodar region, JSC Lengiprorechtrans, JSC Lengiprotrans, JSC LenTISIZ, LLC Metrotunnelgeodeziya, JSC Mosgiprotrans, State Unitary Enterprise Mosgorgeotrest, State Unitary Enterprise Mosinzhproekt, State Unitary Enterprise MosTsTISIZ, LLC Nikolay Ingeo, LLC TyumenNIIgiprogaz ", MU "Center for the Preparation of Permits for Construction" in Yekaterinburg.

CONSIDERED by the Department of Pricing and Estimated Standardization of the Gosstroy of Russia (Stepanov V.A., Grishchenkova T.L.).

INTRODUCED by the Department of Pricing and Estimated Standardization of the Gosstroy of Russia.

APPROVED AND ENTERED INTO EFFECT on January 1, 2004 by Decree of the State Construction Committee of Russia dated December 23, 2003 No. 213.

IN REPLACEMENT of the Collection of prices for survey work for capital construction - M. 1982: part I (tables 8 - 37, 50, 55 - 60, 62 - 73, 77 - 80, 84 - 92); part III, chapter 8 (tables 113, 115 - 119, 122 - 127, 152, 153), chapters 9 - 11; Part VII (Table 403); part VIII (tables 408 - 410, 414, 415, 418 - 420); Appendix 3 (tables 7 - 9, 13, 22, 23); Directory of enlarged basic prices for engineering geodetic surveys for construction - M. 1997

General instructions. 2

Part I. Enlarged base prices for complex engineering and geodetic surveys for construction. 8

General provisions. 8

Chapter 1. Integrated base prices for complex engineering and geodetic surveys during the creation (development) of plan-altitude reference geodetic networks. 9

Chapter 2. Integrated base prices for complex engineering and geodetic surveys when creating engineering and topographic plans. eleven

Chapter 3. Integrated base prices for complex engineering and geodetic surveys for the construction of linear structures. 17

Part II. Basic prices for individual species

engineering and geodetic works. 23

General provisions. 23

Chapter 4. Special shooting. 23

Chapter 5. Surveying existing linear structures. 26

Chapter 6. Surveying, leveling and description of underground and above-ground structures. 36 Chapter 7. Miscellaneous.. 40

geodetic work

Chapter 8. Cartographic and office geodetic work... 52

Chapter 9. Registration of survey work and acceptance of engineering survey materials. 61

Part III.

Basic prices for auxiliary work.. 62

Chapter 10. Auxiliary work... 62

Appendix 1. Coefficients for prices for engineering surveys carried out in desert and waterless areas. 63

Appendix 2. Duration of the unfavorable period of the year for field engineering surveys. 65

Appendix 3. Regional coefficients for wages of employees of design and survey organizations (with the exception of survey expeditions, parties and detachments)68

Appendix 4. Regional coefficients for wages of workers of survey expeditions, parties and detachments. 71

1. Appendix 5. List of regions of the Far North and areas equated to regions of the Far North. 74 GENERAL INSTRUCTIONS Directory of basic prices for

2. engineering survey

for construction. Engineering and geodetic surveys (hereinafter referred to as the “Directory”) is designed to determine the basic cost of engineering and geodetic surveys when setting prices in agreements (contracts).

This Handbook is intended for use by enterprises (organizations) regardless of departmental affiliation and organizational and legal forms:

Performers of survey work for construction who have a license to carry them out;

3. Customers of survey work;

4. Bodies supervising the implementation of survey work. The directory contains: Prices are calculated at the level of the estimated normative base as of 01/01/2001 according to the terms of remuneration of engineers and technical workers and workers, the cost of materials and services, as well as the amount of depreciation charges for fixed assets, in accordance with “ Methodological recommendations on the composition and accounting of costs included in the cost of design and survey products (works, services) for construction and formation Russian Federation dated July 1, 1995 No. 661.

5. Prices are calculated according to the composition and modern technology production of field and desk engineering and geodetic work, taking into account the requirements of GOSTs and current regulatory documents(approved or agreed upon by the State Construction Committee of Russia as of 01/01/2001), and are optimal for determining the cost of these works. Prices include overhead costs, planned savings, contributions for social needs, costs of paying taxes and fees, including local taxes(excluding VAT).

Prices for field work are provided for their implementation in expeditionary conditions with the payment of travel allowances or field allowances to workers.

Prices for office processing of survey materials are provided for their implementation in a hospital setting without paying employees travel allowances or field allowances.

6. Prices are given in rubles and for certain types of work are given in the form of a fraction: above the line is the price of field work, below the line is the price of office work. In other cases, prices are provided separately for field and desk work.

Prices are optimal for the same work. Primary processing of survey materials, carried out under expeditionary conditions, is taken into account in the prices for field work.

The prices also take into account the costs of:

a) receipt of technical specifications for conducting surveys;

b) studying and summarizing the initial data necessary for carrying out research;

c) preparation of contractual documentation;

d) preparation, verification of instruments, tools, equipment and metrological assurance of the uniformity and accuracy of measuring instruments;

e) current repair of equipment and tools;

f) loading and unloading equipment and tools when moving around the site;

g) internal control and acceptance of survey materials;

h) release of survey reporting materials in 4 copies, including 2 copies for the customer and 1 copy for the body that issued the survey permit or carried out their registration;

i) delivery of reporting materials to the customer, as well as in the prescribed manner to the authorities that issued the permit for surveys or carried out their registration;

j) transfer of permanent geodetic signs to monitor their safety and draw up a report.

7. The prices do not take into account and are determined additionally according to the relevant tables (standards) of this Directory, costs for:

a) registration, on behalf of the customer, of permits (registration) for surveys carried out by the organization performing the surveys;

b) internal and external transport;

c) organization and liquidation of work at the site;

d) cutting of clearings and sight lines;

e) taxation of green spaces;

f) collecting information on the inventory of buildings and structures;

h) installation, dismantling and maintenance of special survey equipment;

i) supervision (methodological guidance) of work transferred for execution by subcontractors;

j) preparation and delivery to the customer of intermediate materials of engineering and geodetic surveys;

k) auxiliary work.

8. Prices are calculated for survey conditions in middle lane European part of the Russian Federation (by level wages), a favorable period of the year and a normal mode of survey work.

When determining the estimated cost of surveys carried out in other regions of the Russian Federation, under special regime conditions, as well as during unfavorable periods of the year, the corresponding coefficients are applied to prices:

a) when carrying out surveys in mountainous and high-mountainous areas, the coefficients given in Table 1 are applied to prices.

Table 1

b) when carrying out surveys in desert and waterless areas, the coefficients given in Appendix 1 are applied to the prices for these surveys;

c) when performing research:

In territories with a special regime, a coefficient of 1.25 is applied to prices for field work;

In areas with radioactivity more than 1 mSv/year or 0.1 rem/year - a coefficient from 1.25 to 1.5 depending on the level of radioactivity assessed in accordance with the Radiation Safety Standards NRB-99 (GN 2.6.1.758-99) ;

At night (from 10 p.m. to 6 a.m.), a coefficient of 1.35 is applied to the cost of field work;

At night, in areas with a special regime located in areas with radioactivity more than 1 mSv/year or 0.1 rem/year, the corresponding coefficients are multiplied.

Note - Territories with a special regime include areas and areas where, due to the situation or established regime, interruptions or difficulties associated with loss of working time during surveys are inevitable: border areas, testing grounds, airfields, sites where blasting operations are carried out, areas with heavy dust content in the air , existing construction sites, pits, quarries; environmentally harmful territories and enterprises, territories of explosive, hazardous and hot workshops, territories of enterprises of the defense, chemical, petrochemical, metallurgical, coal and mining industries, oil and gas pumping stations of main pipelines, sensitive enterprises, operating electrical stations and substations, open electrical distribution devices stations, strips up to 200 m wide along existing power lines with a voltage of 500 kV and higher, main streets (avenues) of cities, as well as streets and boulevards of large cities and megalopolises, territories railway stations, ports, backwaters, etc.

d) when performing field survey work, as well as office work carried out in a field camp during an unfavorable period of the year in the relevant areas (according to Appendix 2), the coefficients given in Table 2 are applied to their cost.

table 2

e) when carrying out surveys in regions of the Russian Federation, for which, in accordance with the current legislation of the Russian Federation (according to Appendices 3, 4) or in accordance with the resolution of the Council of Ministers of the RSFSR dated 02/04/91 No. 76, republican, regional, regional and other government or administrative bodies have established regional coefficients for the wages of workers engaged in survey work; the coefficients given in Table 3 are applied to the total estimated cost of these surveys.

Table 3

Regional coefficient to wages

Coefficient to the total estimated cost of surveys

Note - When new regional coefficients for the wages of workers engaged in survey work are introduced after 01.01.01 by law or by directive, the coefficients for the total estimated cost of surveys are determined in accordance with Table 3.

f) when carrying out surveys by organizations making payments related to the provision of benefits to persons working in the regions of the Far North and equivalent areas (according to Appendix 5), as well as in other areas established by current legislation, the corresponding coefficients are applied to the total estimated cost of surveys :

1.5 - when carrying out surveys in the Far North;

1.25 - the same in areas equated to the regions of the Far North;

1.15 - the same in the southern regions of the Irkutsk region, Krasnoyarsk Territory and the Far East (Amur region, Primorsky and Khabarovsk territories), in the Arkhangelsk and Chita regions, the Republics of Buryatia, Karelia, Komi (with the exception of regions of the Far North and areas equated to regions of the Far North).

Note - With the simultaneous application of the coefficients specified in subparagraphs “d” and “f” of paragraph 8, the overall increasing coefficient to the total of the estimated cost of research is determined by summing the unit with the fractional parts of the corresponding coefficients of table 3 and subparagraph “f”.

9. Internal transport costs associated with the transportation of prospectors, equipment and materials from the location of the survey organization (expedition, party, detachment) to the survey site and back, as well as directly at the work site, are determined according to Table 4 as a percentage of the estimated cost of field survey work , as well as office work carried out in a field camp (taking into account the coefficients given in subparagraphs 8 “a”, “b”, “c”, “d” of the General Instructions), including the costs of maintaining survey bases, radio stations, as well as installation , dismantling and maintenance of survey equipment, determined by the prices of tables 82 and 83.

Table 4

Distance from the base of the survey organization, expedition, party or detachment to the survey site, km

Expenses for inland transport, %, with the estimated cost of field survey work, thousand rubles.

St. 75 to 150

St. 150 to 300

St. 300 to 750

Notes : 1. Inland transport costs may be determined based on actual costs in prices of the current period:

a) when performing field survey work in the regions of the Far North and equivalent areas, in sparsely populated (uninhabited) areas (high mountains, desert, taiga, tundra);

b) for the rental and maintenance of special vehicles - airplanes, helicopters, all-terrain vehicles, boats, barges, longboats, reindeer and dog sleds, camels, horse packs, etc.

2. In the case of determining the costs of inland transport in prices of the current period, the standards of Table 4 do not apply.

3. When carrying out surveys of routes of linear structures with a length of more than 100 km, a coefficient of 1.1 is applied to the standards of § 8.

10. External transport costs associated with the travel of workers and the transportation of survey equipment and cargo from the permanent location of the organization performing the survey to the base of the survey expedition, party or detachment (or to the survey site) and back, are determined according to Table 5 as a percentage of the estimated cost of the field survey work, as well as office work carried out under expeditionary conditions (taking into account the coefficients given in subparagraphs 8 “a”, “b”, “c”, “d” of the General Instructions), including inland transport costs determined according to table 4 ( excluding the costs provided for in Note 1 of Table 4), as well as costs for the maintenance of bases and radio stations, installation, dismantling and maintenance of survey equipment, determined at the prices of tables 82 and 83.

Table 5

Travel and transportation distance in one direction, km

Expenses for external transport in both directions, % of the estimated cost of field work, as well as office work carried out under expeditionary conditions, duration, months.

12 or more

St. 25 to 100

Notes : 1. Expenses for external transport for distances up to 25 km are not included in the estimates.

2. The standards of § 1 apply only if it is inappropriate (due to production needs or unfavorable conditions for the travel of workers and the transportation of goods) of daily transportation of survey equipment and workers to the location of the survey organization from the survey site and back.

3. When performing certain types of surveys in unfavorable conditions for travel of workers and transportation of goods to hard-to-reach survey sites and back, external transport costs may be determined based on actual costs in prices of the current period.

4. If expenses are determined in prices of the current period, the standards of Table 5 do not apply.

11. When carrying out surveys in particularly complex natural conditions or in hard-to-reach areas (on the polar islands, in the glacier zone, in high-mountainous, desert, taiga, tundra areas, etc.) for special events (involving climber instructors, guides, organizing a rescue service, etc.) additional expenses that are determined based on actual costs in prices of the current period.

12. They are determined by a separate estimate, drawn up in prices of the current period based on the labor costs of the organization performing the survey and the actual costs of organizations providing services (according to price lists, tariffs, invoices, etc.), and the following expenses are additionally paid by the customer:

To collect (receive, purchase) aerospace, cartographic and other research materials from past years;

Related to the necessary approvals for certain types of field work;

To compensate for the costs of operating organizations when agreeing with them on a plan for underground communications;

For the rental of bases and radio stations during research in the regions of the Far North and equivalent areas, in sparsely populated (uninhabited) areas (high mountains, desert, taiga, tundra);

For the rental of special survey equipment and special vehicles;

To purchase a logging ticket;

For compensation of material damage associated with deforestation during surveys;

Related to compensation to land users for material damage caused due to damage during surveys on their land plots;

To pay for the services of third-party organizations necessary for carrying out engineering surveys.

13. The costs of organizing and liquidating work at the facility are determined in the amount of 6% of the estimated cost of field work, as well as office work carried out under expeditionary conditions (taking into account the coefficients given in subparagraphs 8 “a”, “b”, “c”, "d" of the General Instructions), including costs for internal transport, determined according to Table 4, (except for the costs provided for in Note 1 of Table 4), as well as costs for the maintenance of bases and radio stations, installation, dismantling and maintenance of survey equipment, determined by prices tables 82 and 83.

Notes : 1. The following coefficients are applied to the amount of expenses for organizing and liquidating work, determined under clause 13: 2.5 - for surveys with an estimated cost of up to 30 thousand rubles. or during surveys (regardless of their cost) carried out in areas of the Far North and equivalent areas, as well as in sparsely populated (uninhabited) areas (high mountains, desert, taiga and tundra):

2.0 - for surveys with an estimated cost of over 30 to 75 thousand rubles;

1.5 - the same, over 75 to 150 thousand rubles.

2. When carrying out field surveys at a site continuously for more than one year, the coefficients given in Table 6 should be applied to the amount of expenses for organizing and liquidating work.

Table 6

14. When carrying out field work without paying workers field allowances or travel allowances, a coefficient of 0.85 is applied to the prices for this work.

When performing desk processing of survey materials under expeditionary conditions with payment of field allowances or travel allowances to workers, a coefficient of 1.15 is applied to the prices for these works.

15. Increasing factors are applied to the cost of survey work if necessary:

a) issuing intermediate survey materials to the customer (if provided for in the terms of reference or work program), a coefficient of 1.1 is applied to the cost of these surveys (except for the costs determined under clauses 9 - 13);

b) performing office work using limited-use materials, a coefficient of 1.1 is applied to the prices for these works;

c) performing field work with artificial lighting of reading devices, a coefficient of 1.15 is applied to their cost;

d) drawing up a plan of underground and above-ground structures in color (paints), a coefficient of 1.1 is applied to the cost of the corresponding office work;

e) performing office and cartographic work using computer technology, a coefficient of 1.2 is applied to the cost of the relevant work;

f) performing cartographic work with drawing up plans (longitudinal profiles) in two forms: on magnetic and paper media, a coefficient of 1.75 is applied to their cost.

Note - Simultaneous application of the coefficients provided for in subparagraphs “d” and “f” is not allowed.

16. Expenses for supervision (methodological guidance) of engineering

BASIC PRICE GUIDE

FOR ENGINEERING SURVEYS FOR CONSTRUCTION

ENGINEERING AND GEODESIC SURVEYS

(prices are adjusted to the base level as of 01/01/2001)

Date of introduction 2004-01-01

DEVELOPED FSUE "PNIIIS" (Larina T.A., Rykhlova S.I., Chushkina N.I.), JSC "Institute Hydroproject" (Nikanorov E.A., Kharkov Yu.A.), LLC "NPC Ingeodin" (Kalbergenov G.G., Larin V.V.) with the participation of FSUE "Aeroproekt", Committee for Architecture and Urban Planning of the Krasnodar Territory, JSC "Lengiprorechtrans", JSC "Lengiprotrans", JSC "LenTISIZ", LLC "Metrotunnelgeodeziya", JSC "Mosgiprotrans" , State Unitary Enterprise "Mosgorgeotrest", State Unitary Enterprise "Mosinzhproekt", State Unitary Enterprise "MosCTISIZ", LLC "Nikolai Ingeo", LLC "TyumenNIIgiprogaz", MU "Center for the Preparation of Permits for Construction" in Yekaterinburg.

REVIEWED Department of Pricing and Estimated Standardization of the Gosstroy of Russia (Stepanov V.A., Grishchenkova T.L.).

INTRODUCED Department of Pricing and Estimated Standardization of the Gosstroy of Russia.

APPROVED AND PUT INTO EFFECT from January 1, 2004 by Decree of the State Construction Committee of Russia dated December 23, 2003 N 213.

IN REPLACE Collection of prices for survey work for capital construction - M. 1982: part I (tables 8-37, 50, 55-60, 62-73, 77-80, 84-92); part III, chapter 8 (tables 113, 115-119, 122-127, 152, 153), chapters 9-11; Part VII (Table 403); part VIII (tables 408-410, 414, 415, 418-420); Appendix 3 (tables 7-9, 13, 22, 23); Directory of enlarged base prices for engineering and geodetic surveys for construction - M., 1997.

GENERAL INSTRUCTIONS

1. Directory of basic prices for engineering surveys for construction. Engineering and geodetic surveys (hereinafter referred to as the "Directory") is designed to determine the basic cost of engineering and geodetic surveys when setting prices in agreements (contracts).

2. This Handbook is intended for use by enterprises (organizations) regardless of departmental affiliation and organizational and legal forms:

Performers of survey work for construction who have a license to carry them out;

Customers of survey work;

Bodies supervising the implementation of survey work.

3. The directory contains:

4. Prices are calculated at the level of the estimated regulatory framework as of 01/01/2001 according to the terms of remuneration of engineers and technical workers and workers, the cost of materials and services, as well as the amount of depreciation charges for fixed assets, in accordance with the "Methodological recommendations for the composition and accounting of costs included in the cost of design and survey products (works, services) for construction and the formation of financial results", approved by the State Construction Committee of Russia by letter dated 04/06/1994 N BE-19-10/9, taking into account the changes and additions provided for by the Decree of the Government of the Russian Federation dated July 1, 1995 N 661.

5. Prices are calculated in accordance with the composition and modern technology for the production of field and desk engineering and geodetic work, taking into account the requirements of GOSTs and current regulatory documents (approved or agreed upon by the State Construction Committee of Russia as of 01/01/2001), and are optimal for determining the cost these works. Prices take into account overhead costs, planned savings, contributions for social needs, costs of paying taxes and fees, including local taxes (except VAT).

Prices for field work are provided for their implementation in expeditionary conditions with the payment of travel allowances or field allowances to workers.

Prices for office processing of survey materials are provided for their implementation in a hospital setting without paying employees travel allowances or field allowances.

6. Prices are given in rubles and for certain types of work are given in the form of a fraction: above the line is the price of field work, below the line is the price of office work. In other cases, prices are provided separately for field and desk work.

Prices are optimal for the same work. Primary processing of survey materials, carried out under expeditionary conditions, is taken into account in the prices for field work.

The prices also take into account the costs of:

a) receiving terms of reference for carrying out surveys;

b) studying and summarizing the initial data necessary for carrying out research;

c) preparation of contractual documentation;

d) preparation, verification of instruments, tools, equipment and metrological assurance of the uniformity and accuracy of measuring instruments;

e) current repair of equipment and tools;

f) loading and unloading equipment and tools when moving around the site;

g) internal control and acceptance of survey materials;

h) release of survey reporting materials in 4 copies, including 2 copies for the customer and 1 copy for the body that issued the survey permit or carried out their registration;

i) delivery of reporting materials to the customer, as well as in the prescribed manner to the authorities that issued the permit for surveys or carried out their registration;

j) transfer of permanent geodetic signs to monitor their safety and draw up a report.

7. The prices do not take into account and are determined additionally according to the relevant tables (standards) of this Directory, costs for:

a) registration, on behalf of the customer, of permits (registration) for surveys carried out by the organization performing the surveys;

b) internal and external transport;

c) organization and liquidation of work at the site;

d) cutting of clearings and sight lines;

e) taxation of green spaces;

f) collecting information on the inventory of buildings and structures;

h) installation, dismantling and maintenance of special survey equipment;

i) supervision (methodological guidance) of work transferred for execution by subcontractors;

j) preparation and delivery to the customer of intermediate materials of engineering and geodetic surveys;

k) auxiliary work.

8. Prices are calculated for the conditions of survey work in the middle zone of the European part of the Russian Federation (according to the level of wages), a favorable period of the year and the normal mode of survey work.

When determining the estimated cost of surveys carried out in other regions of the Russian Federation, under special regime conditions, as well as during unfavorable periods of the year, the corresponding coefficients are applied to prices:

a) when carrying out surveys in mountainous and high-mountainous areas, the coefficients given in Table 1 are applied to prices.

Table 1

District name

Coefficient

Mountain and alpine with absolute heights of the surface of the site above sea level, m:

from 1500 to 1700

St. 1700 "2000

1,15

" 2000 " 3000

St. 3000

1,25

b) when carrying out surveys in desert and waterless areas, the coefficients given in Appendix 1 are applied to the prices for these surveys;

c) when performing research:

In territories with a special regime, a coefficient of 1.25 is applied to prices for field work;

In areas with radioactivity more than 1 mSv/year or 0.1 rem/year - a coefficient from 1.25 to 1.5 depending on the level of radioactivity assessed in accordance with the Radiation Safety Standards NRB-99 (GN 2.6.1.758-99) ;

At night (from 10 p.m. to 6 a.m.), a coefficient of 1.35 is applied to the cost of field work;

At night, in areas with a special regime located in areas with radioactivity more than 1 mSv/year or 0.1 rem/year, the corresponding coefficients are multiplied.

Note - Territories with a special regime include areas and areas where, due to the situation or established regime, interruptions or difficulties associated with loss of working time during surveys are inevitable: border areas, testing grounds, airfields, sites where blasting operations are carried out, areas with heavy dust. air, existing construction sites, pits, quarries; environmentally harmful territories and enterprises, territories of explosive, hazardous and hot workshops, territories of defense, chemical, petrochemical, metallurgical, coal and mining industries, oil and gas pumping stations of main pipelines, sensitive enterprises operating power stations and substations, open switchgears of power stations, strips up to 200 m wide along existing power lines with voltages of 500 kV and higher, main streets (avenues) of cities, as well as streets and boulevards of large cities of metropolises, territories of railway stations, ports, backwaters, etc.

d) when performing field survey work, as well as office work carried out in a field camp during an unfavorable period of the year in the relevant areas (according to Appendix 2), the coefficients given in Table 2 are applied to their cost.

table 2

Duration of unfavorable period, months

Coefficient

4-5,5

6-7,5

8-9,5

e) when carrying out surveys in regions of the Russian Federation, for which, in accordance with the current legislation of the Russian Federation (according to Appendices 3, 4) or in accordance with Resolution of the Council of Ministers of the RSFSR dated 04.02.91 N 76, republican, regional, regional and other government or administrative authorities Regional coefficients have been established for the wages of workers involved in surveys; the coefficients given in Table 3 are applied to the total estimated cost of these surveys.

Table 3

Regional coefficient to wages

Coefficient to the total estimated cost of surveys

1,05

1,15

1,08

1,25

1,13

1,15

1,25

1,35

1,45

Note - When new regional coefficients for the wages of workers engaged in survey work are introduced after 01.01.01 by law or by directive, the coefficients for the total estimated cost of surveys are determined in accordance with Table 3.

f) when carrying out surveys by organizations making payments related to the provision of benefits to persons working in the regions of the Far North and equivalent areas (according to Appendix 5), as well as in other areas established by current legislation, the corresponding coefficients are applied to the total estimated cost of surveys :

1.5 - when carrying out surveys in the Far North;

1.25 - the same in areas equated to the regions of the Far North;

1.15 - the same in the southern regions of the Irkutsk region, Krasnoyarsk region and the Far East (Amur region, Primorsky and Khabarovsk territories), in the Arkhangelsk and Chita regions, the Republics of Buryatia, Karelia, Komi (with the exception of regions of the Far North and areas equated to regions of the Far North).

Note - When simultaneously applying the coefficients specified in subparagraphs “e” and “f” of paragraph 8, the overall increasing coefficient to the total of the estimated cost of surveys is determined by summing the unit with the fractional parts of the corresponding coefficients of Table 3 and subparagraph “e”.

9. Internal transport costs associated with the transportation of prospectors, equipment and materials from the location of the survey organization (expedition, party, detachment) to the survey site and back, as well as directly at the work site, are determined according to Table 4 as a percentage of the estimated field cost survey work, as well as office work carried out in a field camp (taking into account the coefficients given in subparagraphs 8 "a", "b", "c", "d" of the General Instructions), including the costs of maintaining survey bases, radio stations, and also installation, dismantling and maintenance of survey equipment, determined according to the prices of tables 82 and 83.

Table 4

Distance from the base of the survey organization, expedition, party or detachment to the survey site, km

Expenses for inland transport, %, with the estimated cost of field survey work, thousand rubles.

up to 75

St. 75 to 150

St. 150 to 300

St. 300 to 750

over

Up to 5

8,75

6,25

3,75

St. 5 to 10

11,25

10,0

8,75

6,25

" 10 " 15

13,75

12,5

11,25

10,0

8,75

" 15 " 20

16,25

15,0

13,75

12,5

11,25

" 20 " 30

18,75

17,5

16,25

15,0

13,75

" 30 " 40

21.25o*

20,0

18,75

17,5

16,25

" 40 " 50

23,75

22,5

21,25

20,0

18,75

" 50 " 100

26,25

25,0

23,75

22,5

21,25

Notes: 1. Inland transport costs may be determined based on actual costs in prices of the current period:

a) when performing field survey work in the regions of the Far North and equivalent areas, in sparsely populated (uninhabited) areas (high mountains, desert, taiga, tundra);

b) for the rental and maintenance of special vehicles - airplanes, helicopters, all-terrain vehicles, boats, barges, longboats, reindeer and dog sleds, camels, horse packs, etc.

2. In the case of determining the costs of inland transport in prices of the current period, the standards of Table 4 do not apply.

3. When carrying out surveys of routes of linear structures with a length of more than 100 km, a coefficient of 1.1 is applied to the standards of § 8.

10. External transport costs associated with the travel of workers and the transportation of survey equipment and cargo from the permanent location of the organization performing the survey to the base of the survey expedition, party or detachment (or to the survey site) and back, are determined according to Table 5 as a percentage of the estimated cost of field survey work, as well as office work carried out under expeditionary conditions (taking into account the coefficients given in subparagraphs 8 “a”, “b”, “c”, “d” of the General Instructions), including expenses for inland transport, determined by table 4 (except for the costs provided for in note 1 of table 4), as well as costs for the maintenance of bases and radio stations, installation, dismantling and maintenance of survey equipment, determined by the prices of tables 82 and 83.

Table 5

Travel and transportation distance in one direction, km

Expenses for external transport in both directions, % of the estimated cost of field work, as well as office work carried out under expeditionary conditions, duration, months

up to 1

12 or more

St. 25 to 100

14,0

11,5

" 100 " 300

19,6

15,4

12,7

" 300 " 500

25,2

21,0

16,8

" 500 " 1000

30,8

25,2

19,6

"1000 " 2000

36,4

32,2

28,0

13,2

St. 2000

39,2

36,4

20,0

16,0

12,0

Notes: 1. Expenses for external transport for distances up to 25 km are not included in the estimates.

2. The standards of § 1 apply only if it is inappropriate (due to production needs or unfavorable conditions for the travel of workers and the transportation of goods) of daily transportation of survey equipment and workers to the location of the survey organization from the survey site and back.

3. When performing certain types of surveys in unfavorable conditions for travel of workers and transportation of goods to hard-to-reach survey sites and back, external transport costs may be determined based on actual costs in prices of the current period.

4. If expenses are determined in prices of the current period, the standards of Table 5 do not apply.

11. When carrying out surveys in particularly difficult natural conditions or in hard-to-reach areas (on polar islands, in the glacier zone, in high mountains, deserts, taiga, tundra areas, etc.) for special events (involving climber instructors, guides, organization of a rescue service, etc.) additional costs may be provided, which are determined based on actual costs in prices of the current period.

12. Determined by a separate estimate, drawn up in prices of the current period based on the labor costs of the organization performing the survey, and the actual costs of organizations providing services (according to price lists, tariffs, invoices, etc.), and the following expenses are additionally paid by the customer:

To collect (receive, purchase) aerospace, cartographic and other research materials from past years;

Related to the necessary approvals for certain types of field work;

To compensate for the costs of operating organizations when agreeing with them on a plan for underground communications;

For the rental of bases and radio stations during research in the regions of the Far North and equivalent areas, in sparsely populated (uninhabited) areas (high mountains, desert, taiga, tundra);

For the rental of special survey equipment and special vehicles;

To purchase a logging ticket;

For compensation of material damage associated with deforestation during surveys;

Related to compensation to land users for material damage caused due to damage during surveys on their land plots;

To pay for the services of third-party organizations necessary for carrying out engineering surveys.

13. The costs of organizing and liquidating work at the facility are determined in the amount of 6% of the estimated cost of field work, as well as office work carried out under expeditionary conditions (taking into account the coefficients given in subparagraphs 8 "a", "b", "c", "d" of the General Instructions), including costs for internal transport, determined according to Table 4 (except for the costs provided for in Note 1 of Table 4), as well as costs for the maintenance of bases and radio stations, installation, dismantling and maintenance of survey equipment, determined according to the prices of the tables 82 and 83.

Notes: 1. The following coefficients are applied to the amount of expenses for organizing and liquidating work, determined according to paragraph 13:

2.5 - for research with an estimated cost of up to 30 thousand rubles. or during surveys (regardless of their cost) carried out in the Far North and equivalent areas, as well as in sparsely populated (uninhabited) areas (high mountains, desert, taiga and tundra):

2.0 - for surveys with an estimated cost of over 30 to 75 thousand rubles;

1.5 - the same, over 75 to 150 thousand rubles.

2. When carrying out field surveys at a site continuously for more than one year, the coefficients given in Table 6 should be applied to the amount of expenses for organizing and liquidating work.

Table 6

Duration of field surveys, months

Coefficient

St. 12 to 16

" 16 " 20

" 20 " 24

over 24

14. When carrying out field work without paying workers field allowances or travel allowances, a coefficient of 0.85 is applied to the prices for this work.

When performing desk processing of survey materials under expeditionary conditions with payment of field allowances or travel allowances to workers, a coefficient of 1.15 is applied to the prices for these works.

15. Increasing factors are applied to the cost of survey work if necessary:

a) issuing intermediate survey materials to the customer (if provided for in the terms of reference or work program), a coefficient of 1.1 is applied to the cost of these surveys (except for expenses determined under clauses 9-13);

b) performing office work using limited-use materials, a coefficient of 1.1 is applied to the prices for these works;

c) performing field work with artificial lighting of reading devices, a coefficient of 1.15 is applied to their cost;

d) drawing up a plan of underground and above-ground structures in color (paints), a coefficient of 1.1 is applied to the cost of the corresponding office work;

e) performing office and cartographic work using computer technology, a coefficient of 1.2 is applied to the cost of the relevant work;

f) performing cartographic work with drawing up plans (longitudinal profiles) in two forms: on magnetic and paper media, a coefficient of 1.75 is applied to their cost.

Note - Simultaneous application of the coefficients provided for in subparagraphs "d" and "f" is not allowed.

16. The costs of supervision (methodological guidance) of engineering surveys (or certain types of survey work) when performed by subcontractors are determined by the organization subcontracting the work, in addition to 5% of the cost of these works (except for expenses determined by paragraphs 8 "c" and "d"; 9-13 of the General Instructions, as well as excluding the cost of performing auxiliary work given in Chapter 10, tables 81-84, aerial photography and services of third-party organizations).

17. When applying several coefficients established by the Directory to prices (costs), the latter are multiplied (with the exception of the coefficients of subparagraphs “e” and “f” of paragraph 8 of the General Instructions).

18. The estimate attached to the contract provides for additional costs for the work and services listed in paragraph 12 of the General Instructions, as well as unforeseen expenses in the amount of at least 10% of the estimated cost of survey work.

19. If it is necessary to urgently carry out survey work, an increasing factor is applied to the estimated cost of the survey, the value of which is established in the contract by agreement of the parties.

20. The prices of this Handbook are adjusted to the level of costs as of 01/01/01. Bringing the base cost of engineering and geodetic surveys to the price level of the current period is carried out by applying to this cost an inflation index determined in the prescribed manner.

21. The inflation index is not applied to expenses determined based on actual costs in prices of the current period. Expenses determined in prices of the current period are included either:

In a separate estimate;

They are included in the general estimate in a separate section and are placed after the line “total estimated cost”, calculated based on the prices of this Directory and reduced to the price level of the current period.

Full version document can be downloaded

The section contains 52 documents:

    Gas equipment and gas supply. External lighting Directory of basic prices for design work for construction. Gas equipment and gas supply to industrial enterprises, buildings and structures. Outdoor lighting. Gas equipment and gas supply are in operation. Manual A practical guide to using the reference price guide for design work for construction. Gas equipment and gas supply to industrial enterprises, buildings and structures. Outdoor lighting. Urban planning documentation is in effect. Manual A manual for determining the construction cost of developing urban planning documentation. Valid Urban planning documentation Directory of basic prices for design work for construction. Urban planning documentation. Operates Iron and car roads . Chapter 4., 2nd edition Directory of basic prices for design work for construction. Railways and roads. Bridges. Tunnels. Subways. Industrial transport. Chapter 4. Artificial structures (2nd edition). Operates Railways and roads. Manual A manual for determining the relative cost of developing design estimates (to the Directory of basic prices for design work for construction. Railways and roads. Bridges. Tunnels. Subways. Industrial transport). Valid Engineering and geodetic surveys Directory of basic prices for engineering and geodetic surveys during the construction and operation of buildings and structures. Valid Engineering-geological surveys Directory of basic prices for engineering-geological and engineering-ecological surveys for construction (instead of Chapters 12, 14 and 15 and table 298 of Chapter 17 of the Collection of prices for survey work for capital construction 1982; Directory of basic prices for l. Valid Engineering-geological survey hydrographic works Directory of basic prices for engineering surveys for construction. Engineering and hydrographic works. Engineering and hydrometeorological surveys on rivers (Enacted into force on January 1, 2001, replacing: Chapter 3 (Tables 62, 63); 5 (Tables 86, 87, 90-92); 6; 7; 8 (Table . Valid Coefficients for wage benefits Recommendations for determining the coefficient for base prices for design work, taking into account the additional costs of organizations for preferential wage payments. Valid for geodetic surveys Directory of consolidated base prices for engineering and geodetic surveys for construction. Valid Measurement work and inspections of buildings. Directory of basic prices for measurement work and inspections of buildings and structures. Valid Inspection of building structures Directory of basic prices for design work on inspection, assessment of technical condition, testing and strengthening of building structures of buildings, structures, cranes and lifts. 2nd edition. Operating water supply and sewerage facilities. Manual A practical guide to using the reference price guide for design work for construction. Water supply and sewerage facilities. Valid Water supply and sewerage facilities Directory of basic prices for design work for construction. Water supply and sewerage facilities. Operating gas industry facilities. Manual A manual for determining the relative cost of developing project documentation. Gas industry facilities (2nd edition). Operating gas industry facilities. Practical guide Practical guide on using the reference price guide for design work for construction. Gas industry facilities (2nd edition). Valid Gas industry facilities Directory of basic prices for design work for construction. Gas industry facilities (2nd edition). Valid Civil aviation facilities Directory of basic prices for design work for construction. Civil aviation facilities. Operating Housing and civil construction projects. Manual A manual for determining the relative cost of developing design estimates. Objects of housing and civil construction. Operating Housing and civil construction projects. Pract. allowance A practical guide to using the reference price guide for design work for construction. Objects of housing and civil construction. Valid Housing and civil construction projects Directory of basic prices for design work for construction. Objects of housing and civil construction. Forestry facilities are in operation. Manual A practical guide to using the reference price guide for design work for construction. Forestry objects. Valid Forestry facilities Directory of basic prices for design work for construction. Forestry objects. Main oil transport facilities are in operation. Manual A practical guide to using the reference price guide for design work for construction. Objects of main oil transportation. Operating Oil main transportation facilities Directory of basic prices for design work for construction. Objects of main oil transportation. Operating facilities of the mechanical engineering industry. Manual A practical guide to using the reference price guide for design work for construction. Objects of the mechanical engineering industry. Valid: Facilities of the mechanical engineering industry Directory of basic prices for design work for construction. Objects of the mechanical engineering industry. Operating oil industry facilities. Manual A practical guide to using the reference price guide for design work for construction. Oil industry facilities. Operating Oil industry facilities Directory of basic prices for design work for construction. Oil industry facilities. Operating Industrial facilities building materials . Manual A practical guide to using the reference price guide for design work for construction. Building materials industry facilities. Operating Objects of the building materials industry Directory of basic prices for design work for construction. Building materials industry facilities. Operating river transport facilities. Manual Practical guidance on the use of a reference book of basic prices for design work for the construction of river transport facilities. Valid River transport facilities Directory of basic prices for design work for construction. River transport objects. Communication objects are in effect. Manual 1. A manual for determining the relative cost of developing design documentation for communication facilities. Communication objects are in effect. Manual 2. Practical guide on the use of the Directory of basic prices for design work for the construction of "Communication Facilities" (General Provisions). Communication objects are in effect. Manual 3. Practical guide to the application of the Directory of basic prices for design work for the construction of "Communication Facilities" (Explanations on the procedure for applying basic prices for design work for the construction of electrical and postal communication facilities - tables 1-10, 22. Valid Communication Facilities Directory of Basic Prices for design work for construction. Communication facilities. Valid Pulp and paper industry facilities. A practical guide to using the reference price guide for design work for the construction of pulp and paper industry facilities. Valid Pulp and paper industry reference book. Pulp and paper industry facilities. Operating Energy facilities. A guide to basic prices for design work for energy facilities. A guide to determining the relative cost of developing design documentation and the unit cost of developing working documentation for buildings, structures and types of work. Operating Energy facilities. Practical guide Practical guide on using the reference price guide for design work for construction. Energy facilities. (main provisions). Active Energy facilities Directory of basic prices for design work for construction. Energy facilities. Operating Enterprises of transport, storage of petroleum products and gas stations Directory of basic prices for design work for construction. Transport enterprises, storage of petroleum products and gas stations. Operating enterprises for transport and storage of petroleum products. Manual A practical guide to using the reference price guide for design work for construction. Transport enterprises, storage of petroleum products and gas stations. Valid Development of documentation for automated process control systems Directory of basic prices for the development of technical documentation for automated process control systems (APCS). Active Development of design documentation. Manual Practical guidance on the use of a reference price guide for the development of design documentation for custom-made equipment. Valid Development of design documentation Directory of basic prices for the development of design documentation for custom-made equipment. Active Development of technical documentation for major repairs Directory of basic prices for the development of technical documentation for major repairs of building structures of buildings and structures. Valid Explanations on the use Explanations on the use of the collection of prices and reference books of basic prices for design work for construction. Fire and security protection systems are in operation. Manual A practical guide to using the reference price guide for design work for construction. Fire and security protection systems. Operating Fire and security protection systems Directory of basic prices for design work for construction. Fire and security protection systems. Valid

State Committee of the Russian Federation

On construction, architectural and housing policy

(Gosstroy of Russia)

Directory of basic prices for engineering and geodetic surveys during construction

and operation of buildings and structures

UDC 624.131.3.003.13:338.5 (083.78)

DEVELOPED BY PNIIIS (candidate of technical sciences Larina T. A., Rykhlova S. I., Kalbergenov G. G., Chushkina N. I., candidate of technical sciences Leonov V. I.), JSC Institute Hydroproject "(Nikanorov E. A., Ph.D. Carlson A. A.), LLC "NPC Ingeodin" (Larin V. V., Prokofiev D. I.) with the involvement of Mosgorgeotrest (Ivanov A. A.), OJSC "Mosgiprotrans" (Zhurov F.F.), OJSC "Giprorechtrans" (Serebryakov M.I.), Atomenergoproekt (Fikhman A.I.).

INTRODUCED by the Production and Research Institute for Engineering Surveys in Construction (PNIIIS) of the State Construction Committee of Russia.

APPROVED by the State Committee of the Russian Federation for Housing and Construction Policy (Gosstroy of Russia) by letter dated June 29, 1998 No. 9-4/84.

GENERAL INSTRUCTIONS

1. The Directory of basic prices for engineering and geodetic surveys during the construction and operation of buildings and structures (hereinafter referred to as the “Directory”) is recommended for determining the basic cost of engineering and geodetic surveys when setting prices in agreements (contracts).

2. This Handbook is intended for use by enterprises (organizations) of various organizational and legal forms that carry out survey work and have a license to conduct it.

3. The Directory contains basic prices (hereinafter referred to as “Prices”) for:

— geodetic stationary observations of deformations of buildings, structures and earth's surface in areas of development of slope processes;

— creation of a geodetic alignment network (base) and mapping out the main axes of buildings and structures;

- geodetic work by definition geometric parameters reconstructed buildings and structures (construction measurements);

- auxiliary work.

4. Prices are calculated based on official salaries of engineering and technical workers, tariff rates workers, the cost of materials and services, depreciation rates for fixed assets as of 01/01/91, taking into account the basic provisions on the composition of costs included in the cost of products (works, services) with amendments and additions provided for by Decree of the Government of the Russian Federation dated 07/01/95 No. 661.

5. Prices are calculated in accordance with the composition, volume and production technology of field and desk engineering and geodetic work, ensuring the creation of reporting documentation that meets the requirements of current regulatory documents (approved or agreed upon by the State Construction Committee of Russia), and are optimal for determining the cost of field and desk work.

Prices for field work are provided for their implementation in expeditionary conditions, i.e. with payment of travel allowances or field allowances to employees.

Prices for office processing of survey materials are provided for their implementation in a hospital setting, i.e. without paying employees travel allowances or field allowances.

6. Prices are given in rubles and for certain types of work are given in the form of a fraction: above the line is the price of field work, below the line is the price of office work. In other cases, prices are provided separately for field and desk work.

Primary processing of survey materials, carried out under expeditionary conditions, is taken into account in the prices for field work.

The prices also take into account the costs of:

A) receipt of technical specifications for conducting surveys;

B) studying and summarizing the initial data necessary for carrying out research;

C) coordination with the customer of the research program (instructions) and preparation of contractual documentation;

D) preparation, verification of instruments, instruments, equipment and metrological assurance of the uniformity and accuracy of measuring instruments;

D) internal control and acceptance of survey materials;

E) delivery of survey reporting materials to the customer.

7. The prices do not take into account and are determined additionally according to the relevant tables (standards) of this Directory and the following costs are provided for in the estimates:

A) internal transport;

B) external transport;

C) organization and liquidation of work at the site;

D) drawing up a program (instructions) and a technical report (conclusions);

D) preparation and delivery of intermediate engineering survey materials to the customer;

E) auxiliary work.

8. Prices are calculated for the conditions of survey work in the middle zone of the European part of the Russian Federation (according to the level of wages), a favorable period of the year and the normal mode of survey work.

When determining the estimated cost of surveys carried out in other regions of the Russian Federation, as well as during unfavorable periods of the year, the corresponding coefficients are applied to prices:

A) when carrying out surveys in mountainous and high-mountain areas, the coefficients given in table are applied to prices. 1.